Electrical as-built documentation: what should your electrician hand over?

The electrical work in a new house or a renovated flat does not end when the sockets are fitted: documentation comes with the handover. The as-built drawing shows how the installation was actually built, and the test reports prove that it is safe. Based on the Hungarian Electrical Safety Regulation (VMBSZ), this article sums up what has to be handed over and what we hand over at the end of our own projects.

In short

  • Initial verification: a new installation must be verified before it is first put into service; at low voltage this is the electrical safety inspection, and arranging it is the contractor’s duty (VMBSZ).
  • Declaration of conformity: issued by the contractor’s responsible site manager, with the test reports attached.
  • As-built drawing: the electrical drawing of what was actually built; under the VMBSZ it is handed over to the operator.
  • Lightning protection: if installed, it gets its own inspection and certificate (EN 62305).
  • With us: we provide the documentation for our own installations, in one folder.

Author: Norbert Madarász, Managing Director and Partner · Updated: 13 November 2026

What is an electrical as-built drawing?

The construction drawing shows how the installation should be built; the as-built drawing shows how it was built: where the cable routes run, where the boxes and outlets are, which circuit is on which protective device, and where the work differs from the design. Changes always happen on site – a moved socket, an extra circuit – so the as-built drawing is what can be used later for extensions and fault finding.

Under the VMBSZ (Decree 40/2017 NGM, Annex 1, point 2.3), the operator must receive the electrical drawings (the as-built drawing), the operating instructions and the declarations of the designer, the design checker and the responsible site manager. In a family house the operator is usually the owner.

According to the fire protection guideline TvMI 12.6, the current copy of the as-built documentation must not be discarded: keep it with the other documents of the house.

What does the VMBSZ require at handover?

The Hungarian Electrical Safety Regulation asks for three things at the end of an installation:

  1. Initial verification before first use (point 1.6 a). For low-voltage installations this is the electrical safety inspection (point 1.13.1), carried out according to the standard for verifying low-voltage installations (point 1.9). Arranging it is the contractor’s duty (point 1.8).
  2. Declaration of conformity (point 1.3): the contractor’s responsible site manager lists the standards and fire protection guidelines applied and any deviations, and the declaration is signed on behalf of the company.
  3. Attachments (point 1.4): the certificate of the initial verification with a detailed test report; for installed lightning protection, its inspection certificate with a test report; cable insulation and other test reports; product conformity documents.

The former shock-protection compliance check (ÉVF) and the fire safety inspection of power installations (EBF) are now combined in the electrical safety inspection (TvMI 12.6, chapter 8). More on the inspection: electrical safety inspection.

Lightning protection: when is a separate report needed?

If the house gets lightning protection (air terminals, down conductors, earthing), it also needs an initial inspection: its certificate and test report are attachments to the declaration of conformity (VMBSZ point 1.4). The Hungarian fire code (OTSZ) links standard lightning protection to the EN 62305 series, and according to TvMI 12.6 the initial inspection is carried out by a qualified inspector based on the construction drawings.

What do we hand over at the end of our own projects?

When we hand over our own installation, the documentation goes to the client in one folder:

DocumentWhat it is for
As-built drawingthe installation as actually built; the next electrician works from it for extensions and fault finding
Circuit list in the distribution boardwhich circuit breaker and RCD protects what
Protective measures and insulation resistance test reportaccording to HD 60364-6 and the VMBSZ; the measurement is done by our partner qualified as an electrical safety inspector
Lightning protection inspection reportif lightning protection was installed
Test sheet of the low-voltage outletsthe network outlet list, each outlet tested and labelled
KNX project fileif the house has a KNX system: the programming belongs to the operator

In the distribution board, the rack and at the outlets, labels are made with a label printer and are durable, so paper and reality match. Low-voltage systems: low-voltage systems; KNX: KNX smart home; boards: distribution board manufacturing.

Do we make as-built drawings for houses wired by others?

We provide as-built documentation only for our own installations: we can only document reliably what we built and saw before it was covered. If you need an as-built drawing for a house or flat we did not build, we recommend MRNK Mérnökiroda (Hungarian).

We do, however, carry out the safety inspection of an existing installation wired by others: the electrical safety inspection gives a certificate and a test report, for example before selling or letting a property.

Related: Electrical installation · Electrical safety inspection · Electrical design · Low-voltage systems

Frequently asked questions

Which documents should an electrician hand over in Hungary?

Under the VMBSZ: the declaration of conformity with its attachments (initial verification certificate with test report, lightning protection inspection if installed, insulation test reports, product conformity documents), and for the operator the electrical drawings – the as-built drawing – and the operating instructions.

Is an electrical safety inspection required before a new house or flat is handed over?

Yes. Under the VMBSZ a new installation must be verified before it is first put into service; at low voltage this is the electrical safety inspection, and arranging it is the contractor’s duty.

What is an electrical as-built drawing?

The drawing of the installation as actually built: cable routes, boxes, outlets, circuits and deviations from the design. It is the basis for extensions and fault finding.

Who issues the declaration of conformity?

The contractor’s responsible site manager. It lists the standards applied and any deviations and is signed on behalf of the company; the test reports are attached.

Is a separate lightning protection report needed?

If lightning protection was installed, yes: the certificate of its initial inspection with a test report is attached to the declaration of conformity. The standard is EN 62305.

How long should the as-built documentation be kept?

According to TvMI 12.6, the current copy of the as-built documentation must not be discarded, so keep it with the other documents of the house.

Do you make as-built drawings for houses wired by others?

No, we provide as-built documentation only for our own installations; for houses we did not build we recommend MRNK Mérnökiroda. We do carry out electrical safety inspections of existing installations.

Let’s talk about your project.

Tell us what you are planning and we will get back to you within a few days.

Get in touch

Cookie settings

Choose what you consent to. We remember your choice for 6 months; change it any time via “Cookie settings” in the footer.

Privacy notice