Power capacity upgrade and three-phase supply: process, cost, paperwork

You need a capacity upgrade when the house supply can no longer carry a new load: an EV charger, a heat pump, an induction hob or solar panels. The request goes to the local distribution operator; in Buda and most of Pest county this is ELMŰ Hálózati (E.ON group). For a low-voltage connection there is no basic connection fee up to a total of 32 A across all phases; above that, the extra is charged. The process takes several weeks, sometimes a few months. We file the request, and our registered electrician partner builds the meter point, to standard and with a test report.

When do you need a capacity upgrade or a three-phase supply?

The main fuse before the meter sets how much current the house can draw at once. If a new large load draws close to full current for hours, the existing supply may not be enough. Typical cases:

  • EV charger – 11 kW charging needs three phases. On a 3×16 A supply, 11 kW only fits alongside the other loads with load management.
  • Heat pump – runs long and hard in the heating season; the H tariff also needs a separately metered circuit.
  • Induction hob, electric water heater, sauna – short but high peak loads.
  • Solar panels – the inverter must match the connection; larger systems often mean a three-phase upgrade.

A phase upgrade replaces a single-phase supply with a three-phase one (e.g. 1×32 A → 3×16 A). A capacity upgrade raises the current per phase (e.g. 3×16 A → 3×25 A or 3×32 A). Often both happen together.

How much power does a connection give?

ConnectionPower (230 V)Sum of phase currentsBasic connection fee
1×32 Aapprox. 7.4 kW32 Anone
3×16 Aapprox. 11 kW48 Aon the part above 32 A
3×25 Aapprox. 17 kW75 Aon the extra above 32 A
3×32 Aapprox. 22 kW96 Aon the extra above 32 A

The fee-free threshold comes from MEKH Decree 13/2025 (VII. 31.), § 11 (4): no basic connection fee is due on a low-voltage connection if the sum of the currents requested per phase does not exceed 32 A. For an upgrade, the additional capacity is charged.

Who is the distribution operator in Buda and the suburbs: MVM, E.ON or Opus Titász?

You request a capacity upgrade from the distribution operator that runs the grid, not from the electricity retailer. Many people search for “MVM capacity upgrade” because household bills come from the universal supplier, MVM Next. The grid, however, belongs to a different operator in each region:

OperatorArea
ELMŰ Hálózati Kft. (E.ON group)Budapest and most of Pest county – so typically Buda and its suburbs too
E.ON Észak-dunántúli and E.ON Dél-dunántúli Áramhálózati Zrt.Transdanubia
MVM Émász Áramhálózati Kft.Northern Hungary
MVM Démász Áramhálózati Kft.South Great Plain (Szeged, Kecskemét, Baja, Békéscsaba areas)
Opus Titász Zrt.East of the Tisza (Hajdú-Bihar, Szabolcs-Szatmár-Bereg, Jász-Nagykun-Szolnok)

ELMŰ Hálózati’s area is described in a 2025 Infostart article. Your operator’s name is printed on your electricity bill; we also check it during the survey.

What is the process for a capacity upgrade?

The operators follow essentially the same procedure; the steps below are based on the ELMŰ Hálózati and MVM Hálózat descriptions:

  1. SurveyWith an electrician, we assess how much power you need now and later (charger, heat pump, solar) and the state of the meter point.
  2. ApplicationThrough the online customer portal or on the application form. With a written authorisation, the registered electrician can also file it. On E.ON’s application form capacity upgrade and meter relocation are separate options.
  3. Technical and economic offer (MGT)The operator sends the technical conditions and the fees. The signed MGT must be returned in time (at ELMŰ, 60 days for an overhead connection).
  4. Connection fee and contractsIf a fee is due, an invoice follows; the connection contracts can only be signed after payment.
  5. Meter point and completion noticeA registered electrician rebuilds or replaces the meter point and reports completion with the connection documentation.
  6. Meter replacement, energisingThe operator fits the new meter and seals it. MVM energises within 8 working days of the completion notice.
If the existing service cable cannot carry the new load, the operator has to build network as well. This is the longest route: permits with other utilities and the municipality.
Old meter point and distribution board in a family house before renovation
An old meter point before renovation: an upgrade often means bringing the meter point up to standard too (meter IDs blurred).
Main distribution board with N and PE busbars, supply cables and main switch
Power: a main board with busbars and supply cables, during installation.

How much does a capacity upgrade cost?

The cost has two parts:

  • The operator’s connection fee. No basic fee up to a total of 32 A; above that, the extra is charged. According to 2025 data this is a net HUF 3,900 per ampere above 32 A; the exact amount is in the MGT.
  • The electrician’s work. Meter point, meter cabinet replacement, main feeder, and if needed changes to the distribution board. We quote this item by item after a site survey.

The price depends mainly on the meter point (is it to standard, is it at the plot boundary), the length of the main feeder and whether a new meter cabinet is needed. Private customers pay 0% VAT, as our company is VAT-exempt. We quote after a site survey or from photos of the meter point and the distribution board.

How long does a capacity upgrade take?

The operator’s procedure takes several weeks, sometimes a few months. Most of the time goes on issuing the MGT and scheduling the meter replacement; network construction takes longer. If an EV charger or heat pump is also being installed, we schedule the work around the operator’s procedure so the house is never left without power.

How does meter relocation work?

Relocating the electricity meter also starts with an application to the operator, following the same procedure. Typically an old meter inside the flat or on the house wall is moved into a standard meter cabinet accessible from outside, often together with a capacity upgrade.

The cost of relocating the meter depends on the cable route, the meter cabinet and the operator’s fees. We quote the price item by item after a site survey.

H tariff and GEO tariff for heat pumps

The H tariff is a discounted rate for heat-pump heating. According to MVM’s declaration form, the conditions are: a separately metered circuit, a permanently connected heat pump, a SCOP of at least 3.4, and a heating season from 15 October to 15 April. According to MVM Émász, an H tariff application counts as a capacity upgrade and is only available to customers on universal supply; so it is worth handling it together with the upgrade.

The GEO tariff is another separately metered heat-pump rate. According to a Klimamate summary it is only available in the ELMŰ and ÉMÁSZ areas and applies all year, but the supply is interrupted twice a day for two hours. Ask your operator whether it can still be requested; the H tariff is available nationwide.

Heat-pump wiring is covered in detail on our heat pump and solar connection page.

What do we take on in a capacity upgrade?

We survey the meter point and the distribution board, calculate the power you need and take care of the paperwork: our registered electrician partner runs the whole process, from the connection and capacity upgrade request through the meter point rebuild to the completion notice. Indoor wiring is done to MSZ HD 60364 and handed over with protection tests and a test report. We work in Buda (districts I, II, III, XI, XII) and its suburbs. Related work: power wiring, EV charger installation, heat pump and solar connection.

Frequently asked questions

How much does a capacity upgrade cost?

It has two parts: the operator’s connection fee and the electrician’s work. If the sum of the phase currents stays within 32 A, there is no basic connection fee; above that the extra is charged, and the amount is in the MGT. The meter point work depends on the site; we quote after a survey.

How long does a capacity upgrade take?

Several weeks, sometimes a few months. If the operator also has to build network, it takes longer.

Do I need an electrician for a capacity upgrade?

Yes. A registered electrician builds the meter point and reports completion. With an authorisation they can also file the application; with us, our registered electrician partner runs the whole process.

How many kW does an EV charger or heat pump need?

An 11 kW EV charger needs a three-phase supply; it fits on 3×16 A with load management, while 22 kW needs 3×32 A. For a heat pump, we calculate the need from the rating plate and the other loads in the house during the survey.

Can the upgrade be handled online?

Yes, the operators accept applications through their online portals, but also on paper forms, by e-mail or by post. The meter point itself still has to be built on site.

How much does meter relocation cost?

It depends on the cable route, the new meter cabinet and the operator’s fees. It starts with an application just like a capacity upgrade, so it is worth doing both together.

Let’s talk about your project.

Tell us what you are planning and we will get back to you within a few days.